Prototype railyard nomenclature

Santa Fe Jack

Member
Jul 20, 2006
253
0
16
63
Lost Almost, New Mexico
All -

Do real railyards have a standard way of naming tracks in the yards? If so, I'd like to emulate it.

What I mean is, say you have a ladder yard, with several tracks in a row. Do they call them track 1, 2, 3, 4, etc.? What if one of those branches? Is it 4a, or 4-1, or something like that? This could get very complicated, with the occasional runaround or crossing track, etc.

I have the main yard lead (up the ladder) as Y0. Ladder tracks off this are Y0-J, Y0-K, Y0-L, etc. A second tier jumper track off Y0-J becomes Y0-JJ.

Then there is the identification of turnouts. In the yard, which all leads off of turnout #1, they are hierarchical, so I have

1
1-1
1-1-1
1-1-2
1-1-3
1-2
1-2-1
1-3
1-4
etc.

Is there anything similar in the real world?

What about at the turntable? I was just going to have T01, T02, ..., T11.

Does every yard have their own system, or is there some standardization to the naming of tracks?
 

brakie

Active Member
Nov 8, 2001
2,827
0
36
76
Bucyrus,Ohio
Visit site
So do..Speaking as a former brakeman the only tracks that has names is:
The rip track
inbound shop track
outbound shop track
inbound engine lead
outbound ready track
engine house lead.
=======================================================
In the yard the name tracks would be limited to
Runner
House
local
caboose/cabin
inbound-followed by a number such as Inbound 4.
Outbound track followed by a number such as outbound 4.Yes both inbound and outbound tracks can have the same number.

The rest of the yard tracks would have numbers.Now IF there is a Eastbound yard and West bound yard then the tracks would have a letter in front of the track number such as E12,E12a or W12 or W12a.
Note there would be 2 or more switch crews for the East Yard and West Yard ..However,a caboose switch crew could work either yard.Of course if there is a East Hump and a West hump then there will be a puller crew for EACH hump.The bowl tracks would have numbers.
 

CCT70

Member
Jun 25, 2003
519
0
16
Usually, tracks are numbered starting at the main line. At least that's how I'm used to it out West here.
 

kutler

New Member
Oct 30, 2007
74
0
6
Well in a way everybody is right.

My experience is tracks are usually numbered from the main track.
For example North 1, North 2, North 3, etc would be immediately adjacent to the main track on a east/west railroad. South 1, etc would start on the south side.

Currently most yards have letter codes unique to thier location. For example all the yard tracks in the town of Ignace On. are prefaced with the code BJCS, so BJCSN1, BJCSN2, etc are modern day refinements of the above example.

More complex yards contain sub-yards. For example in a major terminal A Yard might be the receiveing yard, B yard the Departure yard and C yard the Classification yard. Each would have a ladder of tracks numbered A1, A2, etc in the same example as the first paragraph.

In large cities satellite yards are further lettered as are switching districts. S yard might be a 3 mile long spur track off the main track which services 10 industries.

T yard might be a six track industrial yard where transfer movements might bring cuts of cars from the main yard for local switchers to sort out.

Dave Barrow's Cat Mtn rebuild several years ago was a good example of a city layout with satellite yards and switching districts.

So in short you can designate the tracks any way you like, there's likely a prototype for it!
 

MasonJar

It's not rocket surgery
Oct 31, 2002
5,362
0
36
Ottawa, Canada
Visit site
In the Palmerston, ON yard in the 1950s (and before) they had a track that was sort of a "house" track that was called The Dog Leg simply because that's what it looked like from the pedestrian bridge that crossed over the yard.

I would think that each railroad would have a more or less standard way of naming/numbering their tracks, but that one road's method would not necessarily resemble another's.

Andrew
 

Santa Fe Jack

Member
Jul 20, 2006
253
0
16
63
Lost Almost, New Mexico
It seems that the answer to my question is that there is no standardization. Each yard seems to have developed its own naming scheme. Fair enough -- that leaves me free to do whatever I please without looking foolish. No one would say "Why didn't you follow the standard yard track naming convention?" :)
 

doctorwayne

Active Member
Sep 6, 2005
3,516
0
36
Canada, eh?
At the steel plant where I worked, every track had a number, but many also had common names, such as "the 516 runaround", "the scale track", or "the canyon lead". "One West" was the first siding west of #2 Stripper, but its actual number was something like 317. I think that there were 5 or 6 different Yardmasters within the plant, and each area had their own set of nicknames for the tracks within that district, but the tracks were numbered on a plant-wide basis, with the numbers growing chronologically as the plant grew. So track 350, added fairly recently, could end up right next to track 7, which had been built 50 years earlier. Sometimes, such a track might instead be called 7A, too. Generally, tracks grouped together in a small yard were referred to by their number, unless each was used for one specific purpose, in which case they were known as, for instance, coal track, coke track, ore track, coal empties, and so-on. Likewise for individual tracks within different mills - they were usually referred to by their common names.

Wayne
 

brakie

Active Member
Nov 8, 2001
2,827
0
36
76
Bucyrus,Ohio
Visit site
It seems that the answer to my question is that there is no standardization. Each yard seems to have developed its own naming scheme. Fair enough -- that leaves me free to do whatever I please without looking foolish. No one would say "Why didn't you follow the standard yard track naming convention?" :)


On the PRR in Columbus we had a "Fisher" track.That was for the Fisher Auto Body Plant.
You are correct there is no standardization of yard numbers or names.Some names may be use that no longer serves the industry it was so named..Slaughter House track comes to mind on the old PRR..Some tracks was called the B&O track,the C&O track,the NYC track or the N&W track rather then their number yet we knew where each track was located.

The reason they was called the B&O track,the C&O track,the NYC track or the N&W track is those cars was transfer cars to the above roads.In other words all C&O bound cars was put on the C&O track for transfer to the C&O.When these cars was release a transfer crew would pick these cars up and take them to the C&O.This crew was kept busy making transfer runs to the above roads.About one run to each road in a 8 hour shift..Of course this could end up being a 12 hour day just as easy if the main line traffic was heavy or they had to wait before entering the transfer yard.
 

60103

Pooh Bah
Mar 25, 2002
4,754
0
36
Brampton, Ontario, Canada
Visit site
Larry: I bet they were still called the B&O track, the C&O track and the NYC track for decades after those roads ceased to exist.
(My sister claims that she has to tell people, "I've only lived here for 16 years; I don't know where the roller rink used to be.")